SUA CONSTRUCTION

Seacoast Utility Authority is committed to excellence in customer service. Part of that commitment is to ensure the existing water and sewer infrastructure is replaced on an ongoing and timely basis ensuring reliable utility service to its’ customers. This page provides information on some of the ongoing projects to meet our goal of excellence.

For any construction inquiries, please send an email here.

Lake Park “8A & 8C” Water Main Improvements

    • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life.
    • Abandonment, or removal and disposal of the existing water main.
    • Construction will take place in the Lake Park neighborhoods 8A & 8C between Northlake Blvd and Jasmine Dr.  from Prosperity Farms Rd. / 10th St, east to Flagler Blvd.
    • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
    • Municipality: Town of Lake Park
    • Contractor: TBD
    • Design Engineer: CES Consultants
    • Status: Design
    • Estimated Start Date: Late 2025 / Early 2026.

Horseshoe Acres Water Main Improvements

  • Design Engineer: EAC Consulting, INC
    • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life. Replacing of a ductile iron pipe water main aerial crossing of the canal between Horseshoe Acres and Steeple Chase with HDPE pipe via Horizontal Directional Drill.
    • Abandonment, or removal and disposal of the existing water main.
    • Construction will take place in the Horseshoe Acres neighborhood, including streets Kelso Dr, Nashua Dr., Citation Dr., Damascus Dr., Mongo Way., Swaps Way., Travelers Way., and Needles Dr.
    • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
    • Municipality: Palm Beach Gardens.
    • Contractor:
    • Phase 1: (Water main Crossing Canal) CK Contractors
    • Phase 2: (Whole Neighborhood) TBD
    • Residential Engineer: Holtz Consulting Engineers
    • Phase 1: Under Construction
    • Phase 2: Design
    • Estimated Start Date for Phase 2: Early to Mid 2026.

Lift Station 57 Force Main Replacement

    • Installation of approximately 1,500’ of 6” PVC C900 force main via open cut method, replacing existing ductile iron force main that has reached the end of its useful life.
    • Construction will be in the south west corner of the Mariners Cove development, out to Prosperity Farms Rd, and south to Flamingo Rd / Hood Rd.
    • Municipality: Unincorporated Palm Beach County in the Palm Beach Gardens Area.
    • Construction Engineer: Chen Moore & Associates
    • Status: Pre-Construction.
    • Contractor: CK Contractors.
    • Residential Engineer: Holtz Consulting Engineers.
    • Estimated Start Date: January 2026.

      Harbor Lane Low Pressure Force Main.

        • Installation of a Low Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
        • Construction will take place on Harbor Ln.
        • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
        • Short term lane closures will be required throughout the duration of the project.
        • Municipality: Unincorporated Palm Beach County. In the Palm Beach Gardens Area.
        • Contractor: Jamie Underground
        • Construction Engineer: Chen Moore & Associates
        • Status:Under Construction. 
        • Notice of Construction Flyer

      Juno Isles East Water Main Improvements

      • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life.
      • Abandonment, or removal and disposal of the existing water main.
      • Construction will take place in the Juno Isles neighborhood between U.S. Hwy 1 and Ellison Wilson Rd. from Ascott Rd. and Packwood Rd. south to Ardley Rd. and Juno Isles Blvd.
      • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
      • Municipality: Palm Beach County.
      • Contractor: Amici Engineering Contractors
      • Construction Engineer: Chen Moore and Associates
      • Status: Under Construction

      Donald Ross Road Low Pressure Force Main

      • Installation of approximately 300’ of 3” HDPE Low Pressure Force Main horizontally directional drilled under Donald Ross Rd. Installation of approximately 285’ of 2” low pressure force main from Harbor Ln. to the northeast corner of Old Donald Ross Rd. and Paradise Pointe Rd. Installation of approximately 790’ of 2” low pressure force main from Harbor Ln. to the Northwest corner of Old Donald Ross Rd. and Leeward Way.
      • Construction will be in the areas of the North East Corner of the Azure development parking lot, underneath Donald Ross Rd., and along Old Donald Ross Rd. from Paradise Pointe Rd. to Leeward Way.
      • Municipality: Palm Beach Gardens
      • Contractor: Eastern Pipeline Construction
      • Construction Engineer: Chen Moore and Associate
      • Status: Under Construction

      Leeward Way  Low Pressure Force Main

      • Installation of a Low Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
      • Construction will take place on Leeward Way.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short term lane closures will be required throughout the duration of the project.
      • Municipality: Unincorporated Palm Beach County.
      • Contractor: Lazarus Group
      • Construction Engineer: Chen Moore and Associates
      • Status: Under Construction.
      • Notice of Construction Flyer

      Prosperity Farms Road C-17 Bridge-Water Main Replacement

      • Description: Replacement of 16” and 12” ductile iron pipe water mains, including an aerial crossing.
      • Construction will take place on Prosperity Farms Road from Hummingbird Way, north to Ibis Way.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short term lane closures will be required throughout the duration of the project.
      • Municipality: North Palm Beach.
      • Contractor: TBD
      • Construction Engineer: Chen Moore and Associates.
      • Status: Design.
      • Start Date: TBD.

      Pirates Cove Water Main Replacement and Low Pressure Force Main

      • Description: Replacement of all water main in the neighborhood that has reached the end of its useful life. Relocation and replacement of fire hydrants. Installation of a Low-Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
      • Abandonment or removal and disposal of the existing water main.
      • Construction will take place in the Pirates Cove neighborhood on streets including Kidd Ln., Teach Rd., E. Teach Rd., and Avery Rd.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short-term lane closures will be required throughout the duration of the project.
      • Municipality: Unincorporated Palm Beach County. In the Palm Beach Gardens Area.
      • Contractor: CES / Johnson and Davis. Inc.
      • Construction Engineer: CES Consultants
      • Status: Under Construction. 

      Old Port Cove Main Replacement

      • Installation of approximately 1,700’ of 8” DR-14 C-900 PVC force main. The purpose of this project is to replace the existing asbestos cement force main, that is about 45 years old and has reached the end of its useful life, with a new 8” DR-14 C-900 PVC force main to reduce the potential of a pipe failure in the foreseeable future which would result in the discharge of wastewater to the environmentally sensitive Intercoastal Waterway.
      • Construction will be in Old Port Cove Condominium and along U.S. Hwy 1 just south of Lakeshore Dr. and north of the U.S. Hwy 1 bridge.
      • Municipality: The Village of North Palm Beach
      • Contractor: TBD
      • Construction Engineer: TBD
      • Design Engineer: EAC Consulting
      • Residential Engineer: Holtz Consulting
      • Status: Design
      • Estimated Start Date: May of 2026

      PGA Blvd and Prosperity Farms Rd Force Main

      • Installation of approximately 1,510 linear feet of 18” HDPE force main via directional drill under Prosperity Farms Rd and 160 linear feet of 16” PVC force main via open cut method across PGA Blvd.
      • Construction will take place around the PGA Blvd and Prosperity Farms Rd.
      • Municipality: Palm Beach Gardens
      • Contractor: TBD.
      • Design Engineer: EAC Consulting, INC.
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: April 2026.

      Marina Dr. Force Main and Water Main Replacement

      • Replacement of approximately 1,300 linear feet of existing 6-inch and 8-inch cement asbestos water main with new 6-inch and 8-inch ductile iron pipe (DIP) water main.
      • Replacement of approximately 500 linear feet of 4-inch cast iron force main with a new 6-inch PVC force main.
      • Both the water and force mains are approaching the end of their service life and require replacement to ensure continued reliability and system performance.
      • Construction will take place on Marina Dr. from Yacht Club Dr. north to the end of Marina Dr.
      • Municipality: The Village of North Palm Beach
      • Contractor: Deevan Inc. 
      • Design Engineer: Engenuity Group
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: Early 2026.
      • Marina Drive SUA Flyer

      PGA Blvd Parallel 24″ Force Main at I-95

      • Installation of approximately 3,150 linear feet of 24” HDPE and PVC force main using Directional Drill and Open Cut methods.
      • Construction will take place on the South side of PGA Blvd from the west side of I-95 to Alternate A1A.
      • Municipality: Palm Beach Gardens
      • Contractor: Centerline Utilities, Inc. 
      • Design Engineer: Chen Moore and Associates
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: 2026

      Lift Station 54 Force Main Replacement

      • Replacement of approximately 2,750 linear feet of an old 18” Ductile Iron Force Main that is nearing the end of its useful life with new 24” HDPE and PVC pipe. The new pipe is to be installed using Directional drill and open cut methods.
      • Construction will take place from the Anchorage Park Area, where one of Seacoasts’ Major Lift Stations is located, heading west under the North Palm Beach Waterway, along Ibis Way, and crossing Prosperity Farms Rd.
      • Municipality: The Village of North Palm Beach
      • Contractor: TBD
      • Design Engineer: Chen Moore and Associates
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: 2026

      PLANNING AND FUTURE PROJECTS

      Preliminary planning for pipeline infrastructure replacement is underway. A planning map depicts future projects with estimated dates of construction. Priority is considered by age, failure history, service history, and materials concerning the likelihood/consequence of failure. Where possible, these project delivery dates may be adjusted to coordinate with projects by others to minimize customer inconvenience. Click here for the planning map.

      Lake Park “8A & 8C” Water Main Improvements

        • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life.
        • Abandonment, or removal and disposal of the existing water main.
        • Construction will take place in the Lake Park neighborhoods 8A & 8C between Northlake Blvd and Jasmine Dr.  from Prosperity Farms Rd. / 10th St, east to Flagler Blvd.
        • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
        • Municipality: Town of Lake Park
        • Contractor: TBD
        • Design Engineer: CES Consultants
        • Status: Design
        • Estimated Start Date: Late 2025 / Early 2026.

      Horseshoe Acres Water Main Improvements

        • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life. Replacing of a ductile iron pipe water main aerial crossing of the canal between Horseshoe Acres and Steeple Chase with HDPE pipe via Horizontal Directional Drill.
        • Abandonment, or removal and disposal of the existing water main.
        • Construction will take place in the Horseshoe Acres neighborhood, including streets Kelso Dr, Nashua Dr., Citation Dr., Damascus Dr., Mongo Way., Swaps Way., Travelers Way., and Needles Dr.
        • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
        • Municipality: Palm Beach Gardens.
        • Contractor:
        • Phase 1: (Water main Crossing Canal) CK Contractors
        • Phase 2: (Whole Neighborhood) TBD
        • Residential Engineer: Holtz Consulting Engineers
        • Phase 1: Under Construction
        • Phase 2: Design
        • Estimated Start Date for Phase 2: Early to Mid 2026.

      Lift Station 57 Force Main Replacement

        • Installation of approximately 1,500’ of 6” PVC C900 force main via open cut method, replacing existing ductile iron force main that has reached the end of its useful life.
        • Construction will be in the south west corner of the Mariners Cove development, out to Prosperity Farms Rd, and south to Flamingo Rd / Hood Rd.
        • Municipality: Unincorporated Palm Beach County in the Palm Beach Gardens Area.
        • Contractor:CK Contractors. 
        • Construction Engineer: Chen Moore & Associates
        • Residential Engineering: Holtz Consulting Engineers. 
        • Status: Pre-Construction
        • Estimated Start Date: January 2026.

      Harbor Lane Low Pressure Force Main.

        • Installation of a Low Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
        • Construction will take place on Harbor Ln.
        • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
        • Short term lane closures will be required throughout the duration of the project.
        • Municipality: Unincorporated Palm Beach County. In the Palm Beach Gardens Area.
        • Contractor: Jamie Underground
        • Construction Engineer: Chen Moore & Associates
        • Status: Under Construction.

      Juno Isles East Water Main Improvements

      • Installation of a new water main, water services for each residence, and fire hydrants. Replacing a water distribution system that is reaching the end of its useful life.
      • Abandonment, or removal and disposal of the existing water main.
      • Construction will take place in the Juno Isles neighborhood between U.S. Hwy 1 and Ellison Wilson Rd. from Ascott Rd. and Packwood Rd. south to Ardley Rd. and Juno Isles Blvd.
      • Restoration of all areas disturbed by construction activities, including, but not limited to, roadways, driveways, sidewalks, existing utilities, irrigation, sodding, trees, landscaping, mailboxes, light poles, and thermoplastic striping.
      • Municipality: Palm Beach County.
      • Contractor: Amici Engineering Contractors
      • Construction Engineer: Chen Moore and Associates
      • Status: Under Construction.

      Donald Ross Road Low Pressure Force Main 

      • Installation of approximately 300’ of 3” HDPE Low Pressure Force Main horizontally directional drilled under Donald Ross Rd. Installation of approximately 285’ of 2” low pressure force main from Harbor Ln. to the northeast corner of Old Donald Ross Rd. and Paradise Pointe Rd. Installation of approximately 790’ of 2” low pressure force main from Harbor Ln. to the Northwest corner of Old Donald Ross Rd. and Leeward Way.
      • Construction will be in the areas of the North East Corner of the Azure development parking lot, underneath Donald Ross Rd., and along Old Donald Ross Rd. from Paradise Pointe Rd. to Leeward Way.
      • Municipality: Palm Beach Gardens
      • Contractor: Eastern Pipeline Construction
      • Construction Engineer: Chen Moore and Associate
      • Status: Under Construction

      Leeward Way Low pressure Force Main

      • Installation of a Low Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
      • Construction will take place on Leeward Way.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short term lane closures will be required throughout the duration of the project.
      • Municipality: Unincorporated Palm Beach County.
      • Contractor: Lazarus Group
      • Construction Engineer: Chen Moore and Associates
      • Status: Under Construction.
      • Notice of Construction Flyer

      Prosperity Farms Road C-17 Bridge-Water Main Replacement

      • Description: Replacement of 16” and 12” ductile iron pipe water mains, including an aerial crossing.
      • Construction will take place on Prosperity Farms Road from Hummingbird Way, north to Ibis Way.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short term lane closures will be required throughout the duration of the project.
      • Municipality: North Palm Beach.
      • Contractor: TBD.
      • Construction Engineer: Chen Moore and Associates.
      • Status: Design.
      • Start Date: TBD.

      Pirates Cove Water Main Replacement and Low-Pressure Force Main

      • Description: Replacement of all water main in the neighborhood that has reached the end of its useful life. Relocation and replacement of fire hydrants. Installation of a Low-Pressure Force Main to give residents the ability to connect to SUA’s sewer system.
      • Abandonment or removal and disposal of the existing water main.
      • Construction will take place in the Pirates Cove neighborhood on streets including Kidd Ln., Teach Rd., E. Teach Rd., and Avery Rd.
      • Restoration of all areas disturbed by construction activities, including, but not limited to: Roadways; Driveways; Sidewalks; Existing utilities; Irrigation; Sodding; Landscaping; Mailboxes; Light poles; and Pavement striping.
      • Short-term lane closures will be required throughout the duration of the project.
      • Municipality: Unincorporated Palm Beach County. In the Palm Beach Gardens Area.
      • Contractor: CES / Johnson and Davis. Inc.
      • Construction Engineer: CES Consultants
      • Status: Under Construction. 

      Old Port Cove Force Main Replacement

      • Installation of approximately 1,700’ of 8” DR-14 C-900 PVC force main. The purpose of this project is to replace the existing asbestos cement force main, that is about 45 years old and has reached the end of its useful life, with a new 8” DR-14 C-900 PVC force main to reduce the potential of a pipe failure in the foreseeable future which would result in the discharge of wastewater to the environmentally sensitive Intercoastal Waterway.
      • Construction will be in Old Port Cove Condominium and along U.S. Hwy 1 just south of Lakeshore Dr. and north of the U.S. Hwy 1 bridge.
      • Municipality: The Village of North Palm Beach
      • Contractor: TBD
      • Construction Engineer: TBD
      • Design Engineer: EAC Consulting
      • Residential Engineer: Holtz Consulting
      • Status: Design
      • Estimated Start Date: May of 2026

      PGA Blvd and Prosperity Farms Rd Force Main

      • Installation of approximately 1,510 linear feet of 18” HDPE force main via directional drill under Prosperity Farms Rd and 160 linear feet of 16” PVC force main via open cut method across PGA Blvd.
      • Construction will take place around the PGA Blvd and Prosperity Farms Rd.
      • Municipality: Palm Beach Gardens
      • Contractor: TBD.
      • Design Engineer: EAC Consulting, INC.
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: April 2026.

      Marina Dr. Force Main and Water Main Replacement

      • Replacement of approximately 1,300 linear feet of existing 6-inch and 8-inch cement asbestos water main with new 6-inch and 8-inch ductile iron pipe (DIP) water main.
      • Replacement of approximately 500 linear feet of 4-inch cast iron force main with a new 6-inch PVC force main.
      • Both the water and force mains are approaching the end of their service life and require replacement to ensure continued reliability and system performance.
      • Construction will take place on Marina Dr. from Yacht Club Dr. north to the end of Marina Dr.
      • Municipality: The Village of North Palm Beach
      • Contractor: Deevan Inc.
      • Design Engineer: Engenuity Group
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: Early 2026.
      • Marina Drive SUA Flyer

      PGA Blvd Parallel 24″ Force Main at I-95

      • Installation of approximately 3,150 linear feet of 24” HDPE and PVC force main using Directional Drill and Open Cut methods.
      • Construction will take place on the South side of PGA Blvd from the west side of I-95 to Alternate A1A.
      • Municipality: Palm Beach Gardens
      • Contractor:Centerline Utilities, Inc. 
      • Design Engineer: Chen Moore and Associates
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: 2026

      Lift Station 54 Force Main Replacement

      • Replacement of approximately 2,750 linear feet of an old 18” Ductile Iron Force Main that is nearing the end of its useful life with new 24” HDPE and PVC pipe. The new pipe is to be installed using Directional drill and open cut methods.
      • Construction will take place from the Anchorage Park Area, where one of Seacoasts’ Major Lift Stations is located, heading west under the North Palm Beach Waterway, along Ibis Way, and crossing Prosperity Farms Rd.
      • Municipality: The Village of North Palm Beach
      • Contractor: TBD
      • Design Engineer: Chen Moore and Associates
      • Residential Engineer: Holtz Consulting
      • Status: Pre-Construction
      • Start Date: 2026

      PLANNING AND FUTURE PROJECTS

      Preliminary planning for pipeline infrastructure replacement is underway. A planning map depicts future projects with estimated dates of construction. Priority is considered by age, failure history, service history, and materials concerning the likelihood/consequence of failure. Where possible, these project delivery dates may be adjusted to coordinate with projects by others to minimize customer inconvenience. Click here for the planning map.