Seacoast Construction Northlake

Northlake Blvd. Water And Sewer Force Main Replacement

Water and sewer infrastructure along both sides of Northlake Blvd. from Alt A1A / 10th St on the west to US-1 on the east.
Work is scheduled to begin January 2020 and will last approximately 10 months

  • Lane Closures - Roads will remain accessible but with reduced traffic capacity; expect periodic lane closures. Neighbors will be able to access business and properties during construction. Please follow posted detour signs and drive with caution in the area.
  • Door Hangers - Door hangers will be placed to notify customers at certain points during construction of planned temporary, short-term, water and sewer service shutdowns necessary to safely construction the project. 
  • General Contact Information - Taylor Bomarito, Seacoast Utility Authority’s engineer that designed the project is available to answer your questions  at (904) 760-3064. 
  •  


Taylor Bomarito, Hazen & Sawyer
904.760.3064

 
 
Latest Newsletter
Previous Newsletter
General Information
Seacoast Utility Authority
Customer Service
Human Resources
Water / WasteWater
Finance
Engineering