Task NameDurationStart DateFinish
 Pre Construction Activities 46 days 11/3/2009 1/5/2010
  Shop drawings 1 day 11/3/2009 11/3/2009
  Shop drawing approval 1 day 12/23/2009 12/23/2009
  Bore plan submittal 1 day 12/23/2009 12/23/2009
  Bore plan approval 1 day 1/5/2010 1/5/2010
 
 Construction Activities 174 days 1/4/2010 9/2/2010
  Mobilization 5 days 1/4/2010 1/8/2010
  Directional Bores 75 days 1/11/2010 4/23/2010
  • McArthur Street
8 days 1/11/2010 1/20/2010
 
  • Set up & drill pit
2 days 1/11/2010 1/12/2010
 
  • Pilot drill
1 day 1/13/2010 1/13/2010
 
  • Pipe pull back
3 days 1/14/2010 1/18/2010
 
  • Testing
2 days 1/19/2010 1/20/2010
  • C-17 Canal
10 days 1/21/2010 2/3/2010
 
  • Set up & drill pit
2 days 1/21/2010 1/22/2010
 
  • Pilot drill
3 days 1/25/2010 1/27/2010
 
  • Pipe pull back
3 days 1/28/2010 2/1/2010
 
  • Testing
2 days 2/2/2010 2/3/2010
  •  Earman River
13 days 2/4/2010 2/22/2010
 
  • Set up & drill pit
2 days 2/4/2010 2/5/2010
 
  • Pilot drill
5 days 2/8/2010 2/12/2010
 
  • Pipe pull back
4 days 2/15/2010 2/18/2010
 
  • Testing
2 days 2/19/2010 2/22/2010
  •  Lighthouse Drive
9 days 2/23/2010 3/5/2010
 
  • Set up & drill pit
2 days 2/23/2010 2/24/2010
 
  • Pilot drill
3 days 2/25/2010 3/1/2010
 
  • Pipe pull back
2 days 3/2/2010 3/3/2010
 
  • Testing
2 days 3/4/2010 3/5/2010
  •  Holly Drive
10 days 3/8/2010 3/19/2010
 
  • Set up & drill pit
2 days 3/8/2010 3/9/2010
 
  • Pilot drill
3 days 3/10/2010 3/12/2010
 
  • Pipe pull back
3 days 3/15/2010 3/17/2010
 
  • Testing
2 days 3/18/2010 3/19/2010
  •  Burns Road
12 days 3/22/2010 4/6/2010
 
  • Set up & drill pit
2 days 3/22/2010 3/23/2010
 
  • Pilot drill
4 days 3/24/2010 3/29/2010
 
  • Pipe pull back
4 days 3/30/2010 4/2/2010
 
  • Testing
2 days 4/5/2010 4/6/2010
  •  RCA Blvd.
13 days 4/7/2010 4/23/2010
 
  • Set up & drill pit
3 days 4/7/2010 4/9/2010
 
  • Pilot drill
4 days 4/12/2010 4/15/2010
 
  • Pipe pull back
4 days 4/16/2010 4/21/2010
 
  • Testing
2 days 4/22/2010 4/23/2010
 
 

Open Cut Pipe Installation

118 days 1/11/2010 6/23/2010
  •  Richard Rd Water Plant
19 days 1/11/2010 2/4/2010
 
  • Connect to existing
2 days 1/11/2010 1/12/2010
 
  • main installation
7 days 1/13/2010 1/21/2010
 
  • tie to bore @ 124+37
1 day 2/4/2010 2/4/2010
 
  • tie to bore @ 120+12
1 day 2/4/2010 2/4/2010
  •  H.L. Watkins Middle School
7 days 1/21/2010 1/29/2010
 
  • Mobilize and set up
2 days 1/22/2010 1/25/2010
 
  • tie to bore @ 110+00
1 day 1/21/2010 1/21/2010
 
  • main installation
3 days 1/26/2010 1/28/2010
 
  • tie to bore @ 113+17
1 day 1/29/2010 1/29/2010
  •  Riverside Dr C-17 Canal to Lighthouse Dr
26 days 2/1/2010 3/8/2010
 
  • Mobilize and set up
2 days 2/1/2010 2/2/2010
 
  • tie to bore 
1 day 2/3/2010 2/3/2010
 
  • main installation
15 days 2/4/2010 2/24/2010
 
  • tie to bore 
1 day 3/8/2010 3/8/2010
  •  Riverside Dr Lighthouse Dr to Holly Dr
19 days 2/25/2010 3/23/2010
 
  • Mobilize and set up
2 days 2/25/2010 2/26/2010
 
  • tie to bore 
1 day 3/23/2010 3/23/2010
 
  • main installation
15 days 3/1/2010 3/19/2010
 
  • tie to bore 
1 day 3/22/2010 3/22/2010
  •  Riverside Dr Holly Dr to Burns Rd
31 days 3/23/2010 5/4/2010
 
  • Mobilize and set up
3 days 3/23/2010 3/25/2010
 
  • tie to bore 
1 day 3/26/2010 3/26/2010
 
  • main installation
26 days 3/29/2010 5/3/2010
 
  • tie to bore 
1 day 5/4/2010 5/4/2010
  •  Northcorp Pkwy Burns Rd to RCA Blvd
24 days 5/5/2010 6/7/2010
 
  • Mobilize and set up
2 days 5/5/2010 5/6/2010
 
  • tie to bore 
1 day 5/7/2010 5/7/2010
 
  • main installation
20 days 5/10/2010 6/4/2010
 
  • tie to bore 
1 day 6/7/2010 6/7/2010
  •  RCA Blvd Northcorp Pkwy to PGA Blvd
12 days 6/8/2010 6/23/2010
 
  • Mobilize and set up
2 days 6/8/2010 6/9/2010
 
  • main installation
7 days 6/10/2010 6/18/2010
 
  • connection to existing (2x)
3 days 6/21/2010 6/23/2010
 
  testing and restoration Sub. Completion 120 days 2/5/2010 7/22/2010
  final close out 30 days 7/23/2010 9/2/2010