Riverside Dr. Lift Station Service

 

Updates


January 12, 2017

The bypass pumping operation will commence on Tuesday, January 17, 2017.


January 5, 2017

Due to Holiday delays in material fabrication, the contractor and Seacoast will tentatively reschedule the shut down until January 17.


January 3, 2017

Seacoast Utility Authority will be updating and improving the pump station located on Riverside Drive. The work requires bypass pumping from the manhole adjacent to 3771 and 3761 Dogwood Avenue. A pump will run periodically throughout the day until the improvements are complete. We anticipate the work will take less than two weeks. 

Closures: Sidewalk on Riverside Dr. will be closed for the duration of the project, but we do not expect any road closures at this time.

We appreciate your cooperation while we improve the reliability of sewer service to your neighborhood.